• Rua das Chagas, 20 SL Dto 1200-107 Lisboa, Portugal

Witteveen+Bos – Kazakhstan – Caspian Sea Harbour Construction

TENIZSERVICE LLP

NEW LOADING AND UNLOADING DOCK, CATRO, PRORVA IN THE CASPIAN SEA, KAZAKHSTAN

CASE

TenizService LLP conducted the Project Cargo Transportation Route, including constructing a Quay and Cargo Offloading Facilities at Prorva in Kazakhstan.

TASK

The main contractor was a Joint venture of Chevron and the Kazakh State oil company. The Harbour designer, the Dutch company Witteveen+Bos, subcontracted Geodrive Technology initially for driveability studies and later, due to the Geoproviders´s founder knowledge, awarded the one-year site supervision, including the Pile Static and Dynamic load tests.

The first work stage was the driveability prediction analysis for the concrete piles and sheet piles, assessing:

• Hammer size required, driving time and stresses during driving, especially in tension for the concrete piles with a steel joint.

• The risk of refusal before the target penetration level.

• Outlining the equipment needed for sheet pile installation, including the hammer and eventual pre-drilling procedure.

The second stage was the site supervising, whose main challenges were:

• Hard and heterogeneous soil conditions would create difficulties for the pile and sheet-piling installation.

• The design post-optimisation due to the decision to increase the dredging depth, reducing the previous safety factor, demanding a guarantee of accurate execution.

• Seeking alternative solutions and construction methodologies to ensure the design accomplishment and acceptable timetable.

1st phase on-site – Supervising the sheet pile installation, including pre-drilling activities.

2nd phase on-site – Supervising and analysing the pile Dynamic and statical Load testing for the concrete piling foundation of Deck C and B, followed by the correlation between dynamic (DLT) and static pile (SLT) resistance calculation reporting.

3rd phase on-site – monitoring and later in the office with the design team analysing the pile driving heave effect on the pile bearing capacity, deformation, and overall deck stability.

RESULTS

The combination of a sound knowledge of Geotechnical design and the construction experience of executing was the critical input that led to the work’s success despite all difficulties.

 

July 2016 to July 2017
Prorva, The Caspian Sea, Kazakistan